Work plan
The project runs for 36 months (September 2026 – August 2029) and is organised in five work packages.
WP1 defines the core framework; WP2 and WP3 address explainability, verification and extensions;
WP4 turns the results into a tool and validates it on use cases; WP5 covers management and
dissemination.
WP1. Core framework
Coordinator: Germán Vidal · Duration: Q1–Q8
Define the core framework: the syntax of the probabilistic rule-based formalism, efficient inference methods, and the analysis of relevant properties of the models.
- T1.1 A framework for probabilistic rule-based modeling (M1–M6)
- T1.2 Probabilistic inference (M4–M9)
- T1.3 Basic properties of probabilistic models (M7–M24)
WP2. Interpretability and formal verification
Coordinator: María José Ramírez · Duration: Q3–Q10
Develop approaches for generating explanations for the models defined in WP1, as well as methods for their formal verification.
- T2.1 Generation of justifications (M7–M18)
- T2.2 Interpretability and explainability (M13–M24)
- T2.3 Formal verification (M13–M30)
WP3. Extensions
Coordinator: Alicia Villanueva · Duration: Q2–Q10
Define extensions that increase the expressiveness of the basic formalism, making it more suitable for modeling real-world problems.
- T3.1 Inference in the presence of evidence (M4–M12)
- T3.2 Combining probabilities and constraints (M7–M24)
- T3.3 Modeling dynamic systems (M7–M24)
- T3.4 Interaction with other machine learning systems (M16–M30)
WP4. Validation and experimental evaluation
Coordinator: Raúl Gutiérrez · Duration: Q3–Q12
Integrate the results of WP1–WP3 into a common modeling and inference tool, and validate it on representative use cases.
- T4.1 Development of a modeling tool (M7–M36)
- T4.2 Specification of use cases (M10–M18)
- T4.3 Experimental validation (M19–M36)
WP5. Project management and dissemination
Coordinator: Germán Vidal · Duration: Q1–Q12
Coordinate the project, follow the data management plan, and disseminate the results.
- T5.1 Project management and coordination (M1–M36)
- T5.2 Dissemination of results (M1–M36)
Schedule
Year 1
Year 2
Year 3
Q1
Q2
Q3
Q4
Q5
Q6
Q7
Q8
Q9
Q10
Q11
Q12
WP1. Core framework
T1.1
T1.2
T1.3
WP2. Interpretability and formal verification
T2.1
T2.2
T2.3
WP3. Extensions
T3.1
T3.2
T3.3
T3.4
WP4. Validation and experimental evaluation
T4.1
T4.2
T4.3
WP5. Project management and dissemination
T5.1
T5.2
M1 = September 2026. milestone